Project Change Control
1. Set-up Change Control Settings 1. To Set-up Email Notifications, click the ‘Settings’ tab from the left sidebar of the Project. Once done, go to the ...
Tue, 4 Aug, 2026 at 7:40 PM
1. Assign an Action to a Change Control Request 1. Once a project is selected, click the ‘Change Control’ tab from the left sidebar of the page and the...
Mon, 10 Aug, 2026 at 11:35 AM
1. Update Change Control Action 1. Once a project is selected, click the ‘Change Control’ tab from the left sidebar of the page and then click any Pend...
Wed, 5 Aug, 2026 at 3:38 PM
1. Delete Change Control Action 1. Once a project is selected, click the ‘Change Control’ tab from the left sidebar of the page and then click any Pend...
Mon, 10 Aug, 2026 at 12:10 PM
1. Download Change Control Actions in PDF Format 1. Once a project is selected, click the ‘Change Control’ tab from the left sidebar of the page and the...
Wed, 5 Aug, 2026 at 1:12 PM
1. Send Change Control Actions Details via Email 1. Once a project is selected, click the ‘Change Control’ tab from the left sidebar of the page and the...
Mon, 10 Aug, 2026 at 12:35 PM
1. Change Control Actions Table You can filter list of Action Items for a Change Request item to display with the following options: Owner, Status, From...
Wed, 5 Aug, 2026 at 2:16 PM
1. Time Impact Implementation If approved Change Request has time impact, go to ‘Schedule Module’ and adjust the Task/Activities End Dates or create a...
Wed, 5 Aug, 2026 at 4:00 PM
1. Cost Impact Implementation 1.1 Cost Impact (Contingency) 1. If the type of the approved Change Control Request is ‘Contingency’, click the ‘Budget’ ...
Fri, 7 Aug, 2026 at 5:14 PM
1. Change Controls 1. Once a project is selected, click the ‘Reports’ tab from the left sidebar of the page and then click a ‘Report’ item. 2. In th...
Wed, 5 Aug, 2026 at 6:22 PM