Project Change Control
1. Delete Change Control Before Approval 1. Once a project is selected, click the ‘Change Control’ tab from the left sidebar of the page. Click the '...
Wed, 11 May, 2022 at 6:43 PM
1. Approve Change Control Pre-condition: To approve a Pending Change Request, User must be an approver. 1. Once a project is selected, click the ...
Wed, 11 May, 2022 at 7:08 PM
1. Time Impact Implementation If approved Change Request has time impact, go to ‘Schedule Module’ and adjust the Task/Activities End Dates or create a...
Wed, 11 May, 2022 at 8:18 PM
1. Cost Impact (Contingency Type) 1. If the type of the approved Change Control Request is ‘Contingency’, click the ‘Budget’ Module from the left sideba...
Tue, 24 May, 2022 at 7:28 PM
1. Cost Impact Implementation (Scope Change) 1. If the type of the approved Change Control Request is ‘Scope Change’, click the ‘Budget’ Module from the...
Tue, 24 May, 2022 at 7:28 PM
1. Change Controls 1. Once a project is selected, click the ‘Reports’ tab from the left sidebar of the page and then click a ‘Report’ item. 2. On...
Fri, 20 Nov, 2020 at 7:30 PM