Project Change Control

5.2 Delete Change Control Before Approval
1. Delete Change Control Before Approval 1. Once a project is selected, click the ‘Change Control’ tab from the left sidebar of the page. Click the '...
Wed, 11 May, 2022 at 6:43 PM
5.3 Approve Change Control
1. Approve Change Control Pre-condition: To approve a Pending Change Request, User must be an approver.   1. Once a project is selected, click the ...
Wed, 11 May, 2022 at 7:08 PM
6.1 Time Impact Implementation
1. Time Impact Implementation   If approved Change Request has time impact, go to ‘Schedule Module’ and adjust the Task/Activities End Dates or create a...
Wed, 11 May, 2022 at 8:18 PM
6.2 Cost Impact Implementation
1. Cost Impact (Contingency Type) 1. If the type of the approved Change Control Request is ‘Contingency’, click the ‘Budget’ Module from the left sideba...
Tue, 24 May, 2022 at 7:28 PM
6.3 Cost Impact Implementation (Scope Change)
1. Cost Impact Implementation (Scope Change) 1. If the type of the approved Change Control Request is ‘Scope Change’, click the ‘Budget’ Module from the...
Tue, 24 May, 2022 at 7:28 PM
7.1 Change Controls
1. Change Controls 1. Once a project is selected, click the ‘Reports’ tab from the left sidebar of the page and then click a ‘Report’ item.     2. On...