Schedule Trend:


Trend
Meaning
Improved (Green)If the ‘Actual Percent Complete’  for the Entire Project Progress is greater than the ‘Planned Percent Complete’ for the Entire Project Progress.
No Change (Amber)If the ‘Actual Percent Complete’ for the Entire Project Progress is exactly equal to the ‘Planned Percent Complete’ for the Entire Project Progress.
Worsened (Red)If the ‘Actual Percent Complete’ for the Entire Project Progress is less than the ‘Planned Percent Complete’  for the Entire Project Progress.


Budget Trend:


Trend
Meaning

Improved (Green)

Improved impact to Project - Movement is less than or equal to -5% 

No Change (Amber)

No change to previous period - Movement is greater than -5% but less than +5% (-5% < +5%)

Worsened (Red)

Decline impact to Project - Movement is greater than or equal to +5%


Risk Trend:


Trend
Meaning

Improved (Green)

Decrease in the number of Open Risks in the Project

No Change (Amber)

No change  in the number of Open Risks in the Project

Worsened (Red)Increase in the number of Open Risks in the Project



Issue Trend:


Trend
Meaning

Improved (Green)

Decrease in the number of Open Issues in the Project

No Change (Amber)

No change  in the number of Open Issues in the Project

Worsened (Red)Increase in the number of Open Issues in the Project