Schedule Trend:
Trend | Meaning |
Improved (Green) | If the ‘Actual Percent Complete’ for the Entire Project Progress is greater than the ‘Planned Percent Complete’ for the Entire Project Progress. |
No Change (Amber) | If the ‘Actual Percent Complete’ for the Entire Project Progress is exactly equal to the ‘Planned Percent Complete’ for the Entire Project Progress. |
Worsened (Red) | If the ‘Actual Percent Complete’ for the Entire Project Progress is less than the ‘Planned Percent Complete’ for the Entire Project Progress. |
Budget Trend:
Trend | Meaning |
Improved (Green) | Improved impact to Project - Movement is less than or equal to -5% |
No Change (Amber) | No change to previous period - Movement is greater than -5% but less than +5% (-5% < +5%) |
Worsened (Red) | Decline impact to Project - Movement is greater than or equal to +5% |
Risk Trend:
Trend | Meaning |
Improved (Green) | Decrease in the number of Open Risks in the Project |
No Change (Amber) | No change in the number of Open Risks in the Project |
Worsened (Red) | Increase in the number of Open Risks in the Project |
Issue Trend:
Trend | Meaning |
Improved (Green) | Decrease in the number of Open Issues in the Project |
No Change (Amber) | No change in the number of Open Issues in the Project |
Worsened (Red) | Increase in the number of Open Issues in the Project |