1. Video
You can check the following videos for a walkthrough of importing a MPP file to the Focus HQ Project Schedule.
2. Import Project Schedule from Microsoft Project
1. Open the Microsoft Project application. In Microsoft Project, set the columns to be similar to the fields in Focus HQ.
Please see table below for the Focus HQ Schedule columns to be included, along with its Data Format.
Asterisks (*) indicate required fields.
Focus HQ Schedule Columns | Data Format/ Accepted Values |
ID* | Numeric value Must be unique |
WBS* | Numeric value (Ex. 1) Must be unique |
Title* | 500 characters max |
Actual to Date* | Percentage value |
Start Date* | Data Format: dd/mm/yyyy Date should be within Project Start Date and Project End Date. |
End Date* | Data Format: dd/mm/yyyy Date should be within Project Start Date and Project End Date. |
Predecessors | x:n (line ID : dependency code) Must be an ID within the file |
Participants | Username added in the Project. |
Mark as Project Milestone | Yes or No |
Mark as Portfolio Milestone | Yes or No |
Mark as Activity | Yes or No |
Mark as Deliverable | Yes or No |
Project Phase | Project Phases outlined within Project Settings (only if marked as deliverable) |
Effort | Integer value |
Effort Unit | d (for days) |
Actual Effort | Integer value |
Manually Scheduled | Yes or No |
2. Once done with creating the Project Schedule, you can save the file as MPP.
Go to File > Save As, and select the location of where you want to save the MPP file. Then, name the MPP file.
Or you can click CTRL + S, and a popup is displayed where you can name the MPP file and where you want to save it.
3. Export the updated Project Schedule from MPP as a CSV file.
To export the updated Project Schedule, click File > Save As.
In the location to save the file, click the select the Type to save as ‘CSV (Comma Delimited) (*.csv)’
Leave the file name as its default value, then click the Save button.
For versions of Microsoft Project that need Legacy Formats to be configured, please check this link.
4. After successfully exporting the updated CSV file, upload it to the Focus HQ tool.
To import the updated Schedule, please check this link.