Release Notes: v1.0.26
Release Date: 31 March 2017
The following are the major features included in this release:
- Action Tracking Module
- Action Tracking Module with the Ability to create ‘recurring Master Actions’ and sub-actions, etc (change ‘Action Audit’ name)
- Company Resource Functionality Updates
- Users need a way to adjust a resource ‘company capacity’ based on their ‘holidays’, ‘sick leave’, ‘adhoc internal commitments’, etc. This creates the need for capacity fluctuations during different periods
- Project Resource Functionality Updates
- Users need a way to adjust a resource ‘project capacity’ based on their ‘holidays’, ‘sick leave’, ‘adhoc internal commitments’, etc. This creates the need for capacity fluctuations during different periods
- Project Schedule > To Support Up to WBS Level 6
- We extended our WBS to accept up to WBS 6 levels. This is updated in:
- Manual Add Schedule
- Import MPP
- Import CSV
- Drag and drop to limit to 6 Level
- WBS Filter (in module and Report also)
- CSV/PDF/XML Download
- Import Project (contain module Schedule)
- Company Settings >Team Member Details - Edit Member Designation > Activate/Deactivate User
- This give options to user being deactivated only in 1 company and still active in another company
- Checklist Items > Updates
- Hyperlinks to work properly and direct user to that page
- The 'hover over' to display the 'description'
- Made all of the checkboxes outline thicker and a darker colour so that it is easier to see
- Report Template for default 'WBS'
- To be able to set default WBS level for the project schedule Gantt Chart for each report template
- The user will still be able to update the WBS level inside each report if he wishes to.
- This covers report webview and PDF report
- Resource ‘search box’ functionality in all data tables
- Ability to search within ‘first name’, ‘last name’, ‘project name’ and ‘team name’ (no filter is required, the data entered in the 1 input field looks over these 4 data sets)
- Project Budget - Updates
- Correct Calculation for Planned (Baseline) ETC, Planned (Baseline) FFC and Actual Variance fields in Cost Summary Data Table)
- Correct calculation of Forecast-> To Date for Current Period Filtering, Baseline Budget and Approved Changes fields in Detailed Cost Data Table
- Correct calculation of Cumulative Costs -> Forecast
- Projects > updating "Risks", "Issues “Owner” Field to be Editable
- User can now Edit “Owner” input field for Project Risks and Issues
- Portfolio > Project Status Filter
- Added Project Status filter in Portfolio > Overview >Project Summary
- Added Project Status filter in Portfolio > Budget> Portfolio Cost Summary
Planned Future Releases:
- Customisable Knowledge Base
- Categories, Tiles, content, headings, icons and templates
- Time Tracking
- Track hours of assigned resources inproject
- All Module Data Table Sorting
- Applying column filtering to all data tables within ‘Projects’ and ‘Portfolio’
- Project Schedule> Filter by Participants
- To be able to filter tasks based on Participants
- Portfolio and Project Roles
- To set which roles is required and not in project and in portfolio
- Systemwide Unsaved Data Notifications
- When a User clicks "Cancel", "Back", other buttons/links/menu/modules in the sidebar when the user has not clicked Saved/Updated/Add, etc button to save the current changes made, a Notification pop-up msg should appear to say “ Please note that all Unsaved Data or Changes will be lost"
- In that screen,
- If clicked "Confirm", all unsaved data disappears as if it has not been entered.
- If clicked "Cancel" the user is retained at the page where unsaved data has been entered.