Release Notes: v1.0.32
Release Date: 11 August 2017
- Project Schedule > Create Schedule Task Manually > With Duration instead of End Date
- The ability for user to just input Start Date and enter Duration instead of End Date, then the End Date will be auto calculated.
- Project Schedule > Import CSV > Allow to be imported with a start date and a duration( instead of End Date)
- The ability for user to import CSV Schedule with Start Date and Duration instead of End Date, then the End Date will be auto calculated.
- If with Duration data, End Date column can be empty. If with End Date data, Duration column can be empty.
- If both 'Duration' and 'End Date' columns are filled, we will follow 'End' Date' and auto adjust 'Duration' column.
- Portfolio > Pipeline Management > Lined-Up Projects (Opportunities and Approved Opportunities)
- Show all Opportunity/ Approved Opportunity which is lined up for this Portfolio.
- In Add new Portfolio Screen, we will update Project drop-down to included Opportunity and Approved Opportunity also but only Opportunity/Approved Opportunity which still not be attached to any Portfolio can be selected. Then when user add an Opportunity/Approved Opportunity, it will be presented in 'Lined Up Projects'
- Only New Opportunity and Approved Opportunity is showed in the Lined Up Projects table.
- Portfolio > Add Portfolio Level Issues
- We will add a 'Portfolio Management' functionality that also allows defined user to add Issue for Portfolio level
- Portfolio > Add Portfolio Level Risks
- We will add a 'Portfolio Management' functionality that also allows defined user to add Risk for Portfolio level
- Project Close-Out Report > Customise Close-Out Checklist
- Aside from the default fields, the user will be able to add new fields by creating them in the Settings through the Project Type.
- The existing sections will be the default sections but will have an additional section of 'Lessons Learned’
- The new sections will be added in the Project Close-Out Report sections
- Portfolio Dashboard/ Project Dashboard/ Drag and Drop Tiles and Tooltip Hover Over
- Ability to Rearrange Tiles within the Dashboard by Drag and Drop functionality
- Ability to view Historical Data for 3 previous periods plus current period
- Portfolio Dashboard > Pull-up from Project populated Portfolio Tile
- The ability to select Data Management to Pull Item from Projects under a Sub-Portfolio into the Main Portfolios .
Planned Future Releases:
- Project > Dashboard V2 > Data Table Reporting
- We are building version 2 of the ‘dashboard’, which will allow a user to manage 1 set of data and be able to generate multiple Dashboard Tiles and Data Tables
- Ability to import Data Source spreadsheets/ CSV
- Portfolio > Dashboard V2 > Data Table Reporting
- We are building version 2 of the ‘dashboard’, which will allow a user to manage 1 set of data and be able to generate multiple Dashboard Tiles and Data Tables
- Ability to import Data Source spreadsheets/ CSV