1. Milestone Logic Calculations

The Overall Completion Date Variance for a Milestone not completed is based on the effort/duration to complete the task as per the schedule baseline start and end dates displayed as a % score to be completed per day.  For completed milestones the variance calculation based on the baseline end date – date milestone completed and percentage updated to 100%

 

 

 

Milestone Calculation – Based on today’s date 27/12/2018

Formula:

Sample Calculation:

Step 1 – Calculate planned daily %

100%

milestone duration

Milestone duration = total number of calendar days between milestone start and end dates

     ////

Step 2 – Calculate planned days to complete

100% -  % completed = days to complete

                      Daily planned % (step 1)

100-75 / 16.7% per day = 1.5 days effort required

Step 3 -  Calculate total days delay

 (end date – today’s date) + (days to complete step 2) = days late

(05/11 – 27/12/2018) = 52 days delayed

      

52 delayed days + 1.5 days = 53 days late