1. Schedule Default Assignments with CSV Import


Aside from date valuations, several default values are applied to tasks if the user chooses not to include optional fields in the CSV import file.


Focus HQ Field NamesValues
Mark as Project MilestoneNo
Mark as Portfolio MilestoneNo
Mark as ActivityNo
Mark as DeliverableNo
Baseline Effort0 days
Effort0
Effort Unitdays
Actual Effort0 days
Manually ScheduledYes



If you want to Mark a Task as a Deliverable via CSV Import, assign the value of Mark as Deliverable as "Yes".
After that, assign its Project Phase with the default value of Overall Project.