1. Schedule Default Assignments with CSV Import
Aside from date valuations, several default values are applied to tasks if the user chooses not to include optional fields in the CSV import file.
| Focus HQ Field Names | Values |
| Mark as Project Milestone | No |
| Mark as Portfolio Milestone | No |
| Mark as Activity | No |
| Mark as Deliverable | No |
| Baseline Effort | 0 days |
| Effort | 0 |
| Effort Unit | days |
| Actual Effort | 0 days |
| Manually Scheduled | Yes |
If you want to Mark a Task as a Deliverable via CSV Import, assign the value of Mark as Deliverable as "Yes".
After that, assign its Project Phase with the default value of Overall Project.