1. Schedule Logic and Validation rules
There are a number of date validation rules applied to avoid any schedule tasks and activities being created with invalid dates. The rules vary slightly depending if the schedule is in Phase 3 Kick-off or Phase 4 Execution, below is an overview of the rules that apply to setting up project schedules:
Phase 3 Kick-off
- Pipeline schedule creation is optional and managed via Company Settings ‘Project Lifecycle, but if set the following rules apply when setting up the schedule.
- Start date – no restrictions
- Finish date – one day before Phase 4 Execution Start Date
- Execution Schedule
- Start date – no restrictions (if no Pipeline Schedule date is set) OR
- Start date – one day after Pipeline Schedule end date
Phase 4 Execution
- Pipeline schedule – does not apply as READ ONLY
- Execution Schedule
- Start date – can no longer be changed
- Baseline Finish Date – can only be changed via Change Control Process
- Forecast Finish Date – changed based on user’s access rights.