1. Project Dates within a Pipeline Schedule



1. To view the start and end dates for Pipeline Schedule, navigate to the Project ‘Settings’, from the left sidebar then navigate to ‘Project Life Cycle’

 



 

 

    2. The ‘Project Date’field would show the following:

  • Start Date’ - Displays the earliest date a task can commence
  • Finish Date’ - Displays the latest date a task can finish


    Important Note: 

  • Start date cannot be changed once project is in Phase 3 Kick-off stage
  • End date cannot be more than -1day of start date of Phase 4 Execution 
  • Baseline dates are not available within Phase 3 Kick-off (created in Phase 4)