1. Project Dates within a Pipeline Schedule
1. To view the start and end dates for Pipeline Schedule, navigate to the Project ‘Settings’, from the left sidebar then navigate to ‘Project Life Cycle’
|
2. The ‘Project Date’field would show the following:
- ‘Start Date’ - Displays the earliest date a task can commence
- ‘Finish Date’ - Displays the latest date a task can finish
Important Note:
- Start date cannot be changed once project is in Phase 3 Kick-off stage
- End date cannot be more than -1day of start date of Phase 4 Execution
- Baseline dates are not available within Phase 3 Kick-off (created in Phase 4)