Deliverable
For the Deliverable Progress tile, schedule tasks marked as Deliverable in the schedule will be counted (note that Manual Deliverables which have been created in the Deliverables Module are not included).
Completed

Shows the number of Milestones or Deliverables which are completed.

The total is the total number of Milestones in the project.


Milestone
For the Milestone Progress tile, schedule tasks marked as either Project Milestone or Portfolio Milestone (or both) in the schedule will be counted.
Overdue

Shows the number of Milestones or Deliverables which are . Baseline Overdue

The percentage shows that number as a portion of the total number of Milestones or Deliverables in the project.

The colour will be green if there are 0 Overdue, or red otherwise


Projected Slippage

Shows the number of Milestones or Deliverables which are . Projected to Slip

The number of days shows the  or  respectively. Milestone Slippage Days Deliverable Slippage Days

The colour will be green if there are 0 Projected to Slip, or red otherwise


Next 30 Days
Shows the number of Milestones or Deliverables with Forecast End Date in the next 30 days (ie. today + 30 days).
Complete
A schedule task is completed when the task’s Percentage Complete is 100%.
Baseline Overdue

A schedule task is overdue when:

it is not Complete, and the Baseline End Date is in the . past

If a task does not have a Baseline End Date, then the Forecast End Date is referenced instead.


Projected to Slip

A schedule task is projected to slip when it is expected to be completed late. i.e. the task:

has a Baseline End Date, and not Complete, and the Baseline End Date is in the , and future the Forecast End Date is later than Baseline End Date


Slippage Days

Slippage Days shows how many days late you are expected to complete your entire schedule compared to plan.

Slippage Days is calculated for a set of tasks, S

A = Identify the last Baseline End Date of all S. B = Identify the last Forecast End Date of all S.

The Slippage Days is the difference (in days) between B and A when B > A, otherwise 0.


Milestone Slippage Days

The Slippage Days where S is all Milestone tasks in the schedule that have a Baseline End Date



Deliverable Slippage Days
The Slippage Days where S is all Deliverable tasks in the schedule that have a Baseline End Date